By selecting UK flag, you have now set your site language to English. If you'd like to change your language preference again, simply click on one of the other flags.

Close

こちら Japan flag を選択して頂くと、言語設定が日本語に切り替わります。設定変更後は以下の機能が利用可能です。

  • 日本語版ウェブサイトへのクイックアクセスが可能となり、日本語の刊行物をご覧頂けます。

  • 日本語版が閲覧可能な刊行物や記事については、日本語が優先表示されます。表示言語については Japan flag をご参照下さい。

閉じる 言語設定を切り替えたい場合には、国旗のマークをクリックして下さい。

By selecting Japan flag, you have now set your language to Japanese. This has several benefits, including:

  • Providing quick access to our Japan page, which collates all our Japanese content in one place.

  • Ensures that content is presented to you in Japanese first, if we have an article, publication or webpage available in Japanese. Look out for the Japan flag indicators across the site.

Close If you’d like to change your language preferences again, simply click on one of the other flags.

点击选择 China flag,可将网站语言设置为中文。这能帮助您:

  • 快速访问我们的中国区页面,该页面将有网站内容的中文汇总。

  • 在我们的文章、出版物或者网页有中文版本提供的情况下,确保首先向您展示的是中文版本的内容。您可关注站点上的 China flag 按键。

关闭 点击任意其他国旗,可切换您的语言偏好。

By selecting China flag, you have now set your language to Chinese. This has several benefits, including:

  • Providing quick access to our China page, which collates all our Chinese content in one place.

  • Ensures that content is presented to you in Chinese first, if we have an article, publication or webpage available in Chinese. Look out for the China flag indicators across the site.

Close If you’d like to change your language preferences again, simply click on one of the other flags.

North has merged with Standard Club to form NorthStandard.
Find out more about NorthStandard here or continue on this site to access information and resources.

Force Majeure events during COVID-19

Also available in these languages

Add
PDF

The disruption caused by the COVID-19 pandemic continues to affect vessel owners and charterers’ ability to perform existing contracts. This has resulted in an increased focus on force majeure clauses in charterparties.

As a matter of English law, “force majeure” is purely a contractual term and the scope of its operation is defined by what has been included within the relevant clause of the particular contract.

Force majeure clauses

A force majeure clause must be clearly drafted and will usually include:

  • a list of specific force majeure ‘events’
  • what the remedy (or remedies) will be if a force majeure ‘event’ occurs
  • an obligation to report the ‘event’

Whether the COVID-19 pandemic constitutes a force majeure ‘event’ will depend on the wording of the force majeure clause.

A force majeure clause may include specific wording stating that a pandemic would provide contractual relief to one or both parties; however, it may not be this clear.

Proving force majeure

A force majeure clause will usually provide that performance must be “prevented”, “hindered” or “delayed” by the force majeure ‘event’.  It is for the party seeking to rely upon a force majeure clause to prove that the specific facts fall within the protection of the clause.  They must therefore prove the following:

  • that there has been a force majeure ‘event’ as defined in the specific clause
  • that, because of the force majeure ‘event’, they have been prevented, hindered or delayed (as per the wording of the clause) from performing the contract
  • that the circumstances were beyond their control
  • that there were no reasonable steps that could have been taken to avoid or mitigate the force majeure ‘event’ or its consequences.

The collection of evidence is crucial when seeking to prove force majeure.  Such evidence may include written correspondences, notices, government warnings, communications from an agent or port authority, official publications and news reports.

The impact of COVID-19

Restrictions imposed at ports due to COVID-19 may present immediate issues for owners and charterers in respect of performing a contract and may also result in disputes further down the line.

Contractual issues that may arise include port closures preventing the loading or unloading of cargo or determining when the virus started to circulate in a particular country or region.

Disputes may also arise in respect of whether secondary effects of COVID-19 (for example, lack of pilots or berthing slots) would be covered by a force majeure clause which contains a sweep up provision such as “any other cause outside of [the party’s] reasonable control”.  In instances where performance would not have occurred regardless of the COVID-19 pandemic, causation may also be disputed – as most force majeure clause wording will require proof that performance would have taken place but for the effects of the event.

Check your terms

Owners and charterers wishing to invoke force majeure in respect of COVID-19 will need to closely review the terms of the relevant force majeure clause and should collate all evidence which would help them prove force majeure.

Additionally, they should be careful to follow any reporting requirements set out in the clause.

If you have any claims or queries relating to force majeure, then we recommend you contact your usual FD&D claims handler.

Find out more by reading our earlier article ‘What is Force Majeure?’ here.



Welcome to

We've merged with Standard Club to form NorthStandard, this means a new name and look for us, and even better service, support, and cover for you.

You can find out more about NorthStandard on our new website here. As part of the NorthStandard Group, please continue to use nepia.com for your industry news, publications and expertise as well as club rules and contacts.